Planning a concrete paving project

Points to be considered

  1. Decide on the area to be concreted. Draw up a plan and write in all measurements. Peg out the site. Stretch cord line supported on the pegs to define the area. Now remove all turf and vegetable matter.
Poor soil

Dig out the area

Refill and compact carefully
  1. Determine the finished levels of the work: write them on the plan. Check on drainage required - allow a minimum slope of 20 mm per metre (where drainage is necessary): indicate this on the plan.

Ensure that water will not run:

  • towards house footings
  • into garage or carport
  • into neighbour's property.
  1. Determine thickness (depth) of concrete: write it on the plan, eg: A depth of 100 mm is normal for drive-ways, carports and garages used by passenger vehicles but not for trucks.

Calculate volume of concrete required.

  1. Concrete must be contained by formwork placed along the edges of the area to be formed. Timber boards are generally used and should be properly braced so that the formwork is sufficiently strong to support the weight of the concrete. Joints between boards should be watertight to prevent leakage of cement slurry. Allow for drainage and any other requirements shown on the plan and make sure that the ground is firm and even, particularly under the formboards. Spread a 10-mm layer of sand or fine gravel over the entire area to level it and act as a slip joint between the ground and the concrete.
  2. Decide on the surface finish - remember that a steel floated trowelled finish produces a smooth surface and is best used internally, externally a wood float or broomed finish is advised.
  3. Decide on reinforcement requirements and/or the position of control joints: write it on the plan. Remember, when using reinforcement, it is generally discontinued at the joints to provide crack control.
  4. Assess labour requirements; how many able-bodied helpers will be needed? Determine the delivery time of the concrete to the site. Will the concrete be mixed on site or will pre-mixed concrete be used? Will a concrete pump be required? Remember, if using pre-mixed concrete and/or a concrete pump, check with the pre-mixed concrete supplier the recommended grade of concrete for the particular application, and the maximum time allowed for trucks to stay and discharge the concrete. If the allocated time is exceeded, a surcharge may be incurred.
Consider how thick the slab must be
  1. Assess equipment requirements. Basic tools include shovels or spades, screed board, float, edging tool, jointing tool, wheelbarrows and either plastic sheet or proprietary compound to cure the concrete after it is placed and finished. When mixing the concrete on site, a mechanical mixer is recommended and can be hired from most hire companies. Be sure to order and arrange delivery in advance. Be sure to order materials, eg cement, sand and coarse aggregate, in advance and determine the time and date for delivery.
  2. Ensure that the volume of concrete required to cover the area to be concreted can be handled by the assembled team of Workers in one day. If not, form a joint by placing a form board to ensure that concreting stops at a formed vertical face.
  3. Under a floor slab for a garage, house or covered patio and whenever the floor slab is to be enclosed and have floor coverings, you should install a suitable vapour barrier (plastic sheet) on the ground. The vapour barrier should be overlapped a minimum of 200 mm each time it is joined together - then securely taped to prevent separation. The vapour barrier should also be taped around services such as drainage pipes. Vapour barrier material can be purchased from most builders' supply outlets and major hardware retailers.
Steps

Framework must stand up to concrete poured against it
  1. Determine reinforcement requirements, where it will be positioned and where you will make control joints during the finishing stage. Place reinforcement correctly on bar chair supports. Determine the extent of the work - refer to the plan and pegged out site and ensure that all aspects of the work have been considered. It may be worthwhile, and will cost very little, to form a 1-m x 1-m trial area to test placing, finishing and curing techniques. Furthermore, a small practice strip of unreinforced concrete can be readily removed and disposed of if the desired result is not achieved. If after this assessment of the scope of the work, the job appears too large to handle, call in a concrete contractor and use the plan to instruct him about the work required, otherwise proceed.
  2. Order concrete, if using pre-mixed concrete.
  3. Place, finish and cure the concrete.

IMPORTANT

Do not add water to batched concrete as this will reduce its final strength.

Steps to Remember

  1. Estimate quantity: volume in m³(length x width x depth + 10%)
  2. Order:
  • volume m³(rounded up to nearest 0.2 cubic metre)
  • grade (eg N20)
  • slump (eg 100mm)
  1. Specify:
  • use (eg path, garage floor etc)
  • when using a concrete pump, seek advice as to the recommended concrete grade.

IMPORTANT

If you are unsure of your estimated quantity, confirm measurements (length in metres x width in metres x depth in metres) with the pre-mixed supplier when placing your order.